Cabin upgrade

Bhakti Raghava swami's log cabin needs a proper, covered toilet and bathing facilities.  The original deck will be expanded and enclosed, veranda style.  A bathing facility will be built on the new deck.  A greenhouse will be constructed on the south side of the cabin, connecting the bathing facility with the front door.

Building Tasks

  • rock foundation for deck expansion
  • deck expansion and enclosure
  • bathing facility on west side deck
  • greywater drain to plants and trees
  • boot room for east door
  • new greenhouse for starting seeds on south side
  • general carpentry on cabin and deck

This project must be completed by the first week of August

 

expansion

Project Information
Project Status
not started
Estimated Project Cost
2,000