Waterline

Waterline covers 3500 feet and seven hydrants.  The pipeline, hydrant and various brass fittings for the connections costs over $ 6,000.   The work involved digging up a six feet deep canal.  The first 1500 feet would be the two-inch pipe to the entrance of the Eco Village and the balance of 2000 feet would be the one-inch pipe.

Project Information
Project Status
completed
Estimated Project Cost
13,202
Completion date
2017